Catalogue
Catalogue
We would like to present you our catalogues of shower drainage
| Polski | English | Deutsch | Russian |
| Floor drains PL | Floor drains EN | Floor drains DE | Floor drains RU |
You can also download prices list of our floor drains.
Installation instructions
| Polish | English | Deutsch |
| Montaż Instrukcja [PL] | Installation Manual [EN] | Installationsanleitung [DE] |
Installation instructions of linear drainage.
1. Preparation of ground
The main surface of the drain has to be secured with a tape (paper tape), in case of damage during installation. The nex thing that has to by done, is connection the drain with an air trap, in such a way that putting the rubber seal between the air trap and the drain would be possible. Next direct the air trap pipe into the sewage system pipes direction.
2. Connection with sewage system.
Air trap has to be connected with sewage system pipe. If sewage system pipes are of different size, reduction pipes have to be used.
3. Placing of the drainage.
Put the drain in propper position in such a way that the top of the drainage would be about 2mm below planned surface of tiles. Put some joint to keep this position. Check the position and if something is wrong correct it. Connect the drainage using installation joint with the ground.
4. Drain isolation.
Use liquid foil around the drainage and on it's sides. Than put the isolation tape, and cover it with liquid foil again.
5. Finishing.
After all the steps, the drainage is ready to put tiles joint. CAUTION. The gap between the drainage and the tile has to be left and than filled with silicon joint.